Table 11.2:

Recommended Schedule and Order of Magnitude
Cost Estimates for Long Term Improvements

 

Priority

Improvement

Cost Estimate

1

Widen Highway 12 to four lanes east to 45th Street.

$2,000,000

2

Widen Highway 2A through the Town.

$5,750,000

3

Construct 63rd Avenue between C&E Trail and 58th Street.

$4,000,000

4

Re-connection of C&E Tr between 54th Ave and Woodland Dr.

$1,500,000

5

Re-construct Wolf Creek Drive between Highway 2Aand Highway 12 as a four lane industrial major roadway.

$2,250,000

6

Highway 2A service road improvements at Woodland Drive.

$375,000

7

Highway 2A service road improvements at 63rd Avenue.

$250,000

8

Highway 2A service road improvements at Dicken’s Lane.

$50,000

9

Construct West Side Rd between Highway 12 and 63rd Avenue.

$2,750,000

10

Construct 46th Avenue between C&E Trail and 58th Street.

$500,000

11

Re-construction of Highway 12/Wolf Creek Drive intersection and service road intersection (north side).

$1,000,000

12

Re-construction of Highway 12/West Side Road intersection.

$2,000,000

13

Re-construction of Hwy 12/45th St and service road int. (n. side).

$385,000

14

Construct Wolf Creek Drive south of Hwy 12 to 46th Avenue.

$1,500,000

15

Construct 58th Street extension east to C&E Trail.

$3,750,000

16

Signalization of additional intersections as per Table 8.7.

$150,000 - $200,000 each

 

Note:

Note that these estimates do not include shallow utilities, professional design fees, land/easement acquisition, soil reclamation or other third party costs. Note also that these cost estimates are representative of “typical” construction projects and do not reflect all topographic, hydrographic or other details. More detailed functional planning studies would be required in order to more accurately assess these construction costs. Of particular note is the extension of 63rd Avenue west to 58th Street.